Connector Insert Tell you how to organize the inspection and power supply of customer projects?
Answer: The work procedures for organizing the new power supply of customers are as follows.
(1) After the customer provides the following information, the completion inspection will be organized: ① Completion report; ② Primary and secondary drawings that meet the site; ③ Factory instructions and factory test reports of electrical equipment; ④ Relevant regulations and lists of operators for on-site operation and operation management; ⑤ Safety tools, test reports and hidden project reports.
(2) After receiving the above information, organize the relevant personnel of the power supply and user units and the design and construction units to go to the site for acceptance, hold a start-up meeting, put forward inspection opinions, determine improvement methods and completion dates, determine the power supply date, and issue meeting minutes after the consent of all parties.
(3) After the power user unit improves according to the contents of the minutes, a review will be conducted.
(4) The power user inspection personnel will organize the installation of energy meters, dosing devices and relay protection commissioning according to the determined power supply date.
(5) Send the power supply approval or dispatch agreement formulated by the relevant power dispatch unit to the relevant units.
(6) After the preparatory work is completed, the electricity inspection and relevant personnel will go to the site to participate in the guidance of power supply. After the power supply is completed according to the prescribed steps, check that all equipment, instruments, and measurements are normal, make relevant records, and forward the relevant work orders to the relevant units.